Temporary Fuel Storage Area

Temporary Fuel Storage Area

Timeline of works on Temporary Fuel Storage Area
https://www.https://authoritating.com/20180326072954im_/https://sainthelenaaccess.com/news/wp-content/tn3/2/1-Temp-Fuel-Storage-2003121.jpg
  • Temporary Fuel Storage Area – Mar 2012

    Levelling of site for Fuel Tanks
  • Temporary Fuel Storage Area – Apr 2012

    Laying of reinforcement
  • Temporary Fuel Storage Area – Apr 2012

    Start of concreting bond for Tank 1
  • Temporary Fuel Storage Area – Apr 2012

    Concreting of bond for Tank 2
  • Temporary Fuel Storage Area – May 2012

    Start of erection for Tank 1
  • Temporary Fuel Storage Area – May 2012

    Erecting Tank 1
  • Temporary Fuel Storage Area – May 2012

    Erecting Tank 2 and concreting of bond for Tank 3
  • Temporary Fuel Storage Area – May 2012

    Erection of Tanks 1, 2 & 3 and start of reinforcing for Tanks 4 & 5
  • Temporary Fuel Storage Area – May 2012

    Near completion of Tank 1, 2 & 3, reinforcing for Tanks 4 & 5
  • Temporary Fuel Storage Area – Jun 2012

    Basil Read Temporary Fuel Storage & Solomon’s Bulk Fuel Installation
  • Temporary Fuel Storage Area – Jun 2012

    Construction of Tank 4, start of Tank 5
  • Temporary Fuel Storage Area – Jun 2012

    Tank 5 start of concreting for bond
  • Temporary Fuel Storage Area – Jul 2012

    Tank 5 near completion of construction
  • Temporary Fuel Storage Area – Aug 2012

    Side view of Tanks 1, 2 & 3
  • Temporary Fuel Storage Area - Dec 2012

  • Temporary Fuel Storage Area - Dec 2012

 

To view larger photos, click on each gallery’s maximize button:

Look for this maximize button in the lower righthand corner of each gallery page to view larger versions of each photo.

Return to Gallery List