Temporary Fuel Storage Area – Mar 2012
Levelling of site for Fuel Tanks
-
Temporary Fuel Storage Area – Apr 2012
Laying of reinforcement
-
Temporary Fuel Storage Area – Apr 2012
Start of concreting bond for Tank 1
-
Temporary Fuel Storage Area – Apr 2012
Concreting of bond for Tank 2
-
Temporary Fuel Storage Area – May 2012
Start of erection for Tank 1
-
Temporary Fuel Storage Area – May 2012
Erecting Tank 1
-
Temporary Fuel Storage Area – May 2012
Erecting Tank 2 and concreting of bond for Tank 3
-
Temporary Fuel Storage Area – May 2012
Erection of Tanks 1, 2 & 3 and start of reinforcing for Tanks 4 & 5
-
Temporary Fuel Storage Area – May 2012
Near completion of Tank 1, 2 & 3, reinforcing for Tanks 4 & 5
-
Temporary Fuel Storage Area – Jun 2012
Basil Read Temporary Fuel Storage & Solomon’s Bulk Fuel Installation
-
Temporary Fuel Storage Area – Jun 2012
Construction of Tank 4, start of Tank 5
-
Temporary Fuel Storage Area – Jun 2012
Tank 5 start of concreting for bond
-
Temporary Fuel Storage Area – Jul 2012
Tank 5 near completion of construction
-
Temporary Fuel Storage Area – Aug 2012
Side view of Tanks 1, 2 & 3
-
Temporary Fuel Storage Area - Dec 2012
-
Temporary Fuel Storage Area - Dec 2012
To view larger photos, click on each gallery’s maximize button: